New Delta Gutter Project
The activities mainly consisted on:
Civil:
- 60,000 m3 of earthworks (combination of wet and dry)
- Dewatering (deep well & return drainage)
- 77 Vibro piles Ø 406/450 mm length 22 m
- 812 Vibro combination piles Ø 508/610 mm length 31 m
- 14,000 m2 sheet piles
- 6,500 m3 of concrete foundations and floors
- 7,500 m3 of concrete walls
- 1,000 tons of reinforcing steel
- 750 m1 joints (watertight)
- Workshop 48x29x12 m
- Operational building 40x9x6 m
- Third Party Coordination