The construction of the new truck load station.

Koole TTLR2

The work consisted mainly of:

The work consisted mainly of:

All civil and piping & mechanical works for the new truck loading station 2 which will replace the existing loading station.

TTLR2 consisted of 10 loading stations and is capable of handling the following products:

  • Gasoline euro 95 (E10);
  • Gasoline euro 98;
  • Diesel (B7)
  • GTL


Activities:

Civil:

  • Groundworks and drainage;
  • Sewer works (HDPE ø 160 mm – ø 500 mm approximately 700m1);
  • Piling (157 Fundex piles);
  • Construction of a foundation for the truck loading facility;
  • Construction of foundations for additive tanks (approximately 30.60*13.70m);
  • Realization of a waste water basin (app. 16.50*9.50*2.60m);
  • Several foundations for pipe bridge;
  • Construction of a foundation for the substation (app. 15.00*6.00m)
  • Construction of the foundation for a firefighting container (app. 10.00 * 4.00m).

piping & mechanical works

  • Placing of 12 additive tanks;
  • Placing of pumps;
  • Installation of loading skids at the truck loading stations;
  • All piping works (prefab and on site);
  • Hydro testing and NDT testing;
  • Painting works;
  • Scaffolding;
  • Isolation and tracing.