Replacement R-201 C Furnace
The activities mainly consisted on:
Multi-D works;
- Demolition work and site preparation;
- Dismantling of existing pipes;
- Installing steel tubular piles;
- Excavation work;
- Realization of concrete foundations;
- Supply and application of precast concrete beams;
- Pavement;
- Creating tie-ins;
- Prefabrication and assembly of new pipes (incl. Supports);
- Painting works;
- NDT activities;
- Hydro testing;
- Dressing of the four sections of R-201C (channels and platforms);
- Assembly of oven sections (incl. seal welding);
- Welding of pipes;
- Stack mounting (incl. internal welding);
- Coordination.